01
Durham Mine Substation overhaul
INGAGARA successfully completed a 6-week overhaul of the Durham Mine substation 1. We upgraded key switchgear, cables and HVAC equipment to ensure compatibility with a 5MVA onsite solar plant. The project improved power reliability supported hybrid power supply and aligned the substation with morden efficiency and sustainability standards.
Project manager: Nqabayethu Maphenduka
Project duration: 6 Weeks
02
Tshongokwe Brick Factory 20kVA solar project
We undertook a 20kVA off grid solar project from the design, procurement, building and commissioning stages. The client is a brick manufacturer based in Lupane District in Matabeleland South, Zimbabwe. The system reduced diesel dependence, lowered operating costs for the client and guaranteed consistent production in a remote community.
Project manager: Nqabayethu Maphenduka
Project duration: 5 Days
03
Mzola 5 Primary School 5kVA solar project
INGAGARA designed and installed a 5kVA off grid solar system at Mzola 5 Primary School in Lupane District, Matabeleland South. The project included the procurement and installation of a Starlink Mini kit, Wi-fi repeaters and a subnetted network to enable reliable internet access across classrooms and the surrounding areas in support of digital learning. Furthermore, the project provided the foundation for the e-learning initiative from World Vision Zimbabwe aimed at improving digital inclusion for underserved communities.
Project manager: Mphathisi Ngulube
Project duration: 2 Days
04
Mahongola Lithium Mine Borehole Project
INGAGARA is proud to have completed the Engineering, Procurement, Installation and Commisioning of a solar powered borehole system to supply portable water to the Mahongola Lithium Mine staff quaters, dining hall and offices. The system included a 2.2kVA submerssible pump powered by 6 x 510 W solar panels, a 2.2KW Delta VSD, an intergrated tank stand and 2 x 10000 litre Jojo tanks.
Project manager: Nqabayethu Maphenduka
Project duration: 6 Days